City HallTop story
U-M regents consider a computing center budget of up to $785 million as Ypsilanti Township asks for a pause
The computing center plan by the numbers
- $785 million
- is the most the construction budget could reach
- $450 million
- is the estimated cost of the first phase
- $100 million
- in state grant funding
- 144 acres
- off Textile Road
Sources: The Sun Times News, mlive
If you've been following U-M's plan for a research computing center, today's the day. The Board of Regents will consider a construction budget of up to $785 million for the site in Ypsilanti Township, with Los Alamos National Laboratory expected as its principal tenant.
Township officials want a pause. Brenda Stumbo urged residents to ask the regents to wait: "We need time, and we need to pause on this decision." She said the township will litigate to stop the facility if necessary.
- First phase: about 150,000 square feet, expected done fall 2031
- Above-ground construction: could begin late 2027
- Water: up to 650,000 gallons a day at peak demand
- Partnership framework: due to regents by March 31, 2027
The completed center could reach 300,000 square feet
Floor area of the completed center, beside places you know
5 football fields would fit inside the completed center
Source: The Sun Times News
View as table
| Floor area | |
|---|---|
| The completed center | 300,000 sq. ft. (Could reach at full size) |
| A football field | 57,600 sq. ft. (end zones included) |
| A Walmart Supercenter | about 180,000 sq. ft. |
University officials outlined the project at a press conference. The university is also studying potential noise and environmental impacts as the design moves forward. Township officials will host a public panel on the facility hours after the vote.