Latest issueMichigan stuns No. 4 UCLA in triple overtime, 18-16Read now

← Ann Arbor news

Data CenterFriday, November 13

Saline Township trustees reaffirm Oracle's 12-year tax break for its data center

The Daily Ann Arbor teamFrom the Nov. 13 edition · 1 min read · 3 sources

ShareEmailFacebookX

If you've followed the Oracle data center in Saline Township, trustees voted 5-0 on Nov. 11 to reaffirm its 12-year, 50% tax break, after more than an hour of criticism from residents and local officials. They also ratified the where the project is being built. The data center, known as The Barn, is under construction for OpenAI and Oracle.

Township attorney Laura Genovich said the extra hearings were held "out of an abundance of caution." Attorney Ellis Boal, who represents resident Kathryn Haushalter, told trustees, "Those deadlines have passed and cannot be corrected now."

Most of Oracle's $43.1 billion investment is equipment

Source: The Sun Times News

View as table
AmountShare
Equipment and other personal property$33.2 billion77%
Buildings and other real property$9.9 billion23%

“You are granting a multibillion dollar corporation a tax abatement that they do not need.”

Yousef Rabhi, Washtenaw County commissioner and Ann Arbor's next mayor
  • Still needed: approval
  • Oracle projects 450 permanent jobs
  • About 50 people attended two public hearings

Saline Township has voted on the district and exemption several times

  1. Sept. 2025Trustees vote 4-1 to reject rezoning for the data center.
  2. Oct. 2025Trustees vote 4-0 to establish the .
  3. July 2026Trustees approve Oracle's tax exemption application.
  4. Nov. 11Trustees vote 5-0 to reaffirm both approvals.

Sources: The Sun Times News, mlive, The Detroit News

Read it in the full edition

More from the Nov. 13 edition

Read the edition